Saturday, November 23

SDX Energy Kicks Off KSR-15 Well At Sebou Project

Google+ Pinterest LinkedIn Tumblr +

Proactive Investors

KSR-15 is the second of nine planned new wells in SDX Energy’s current drill campaign in Morocco.

SDX Energy Inc (LON:SDX, CVE:SDX) told investors that drilling is now underway on the KSR-15 well at the Sebou project area in Morocco.

KSR-15 is a development well that will take 21 to 30 days to drill and complete, prior to a flow test and connection to existing production facilities (with those operations expected to take up to 30 additional days).

WATCH: SDX Energy’s Paul Welch confident of strong flow rates from latest Morocco discovery

It is the second of nine planned new wells in the current drill campaign in Morocco, spanning the Sebou, Gharb Centre and Lalla Mimouna permits.

Additionally, SDX highlighted that the recently drilled KSE-14 well is due to be put on production within the next ten days.

Share.

About Author

Comments are closed.